1st November 2023 Report
Tower A -
- 1). External sit-out railing - completed all floors
- 2). Tiles work - flooring completed all floor
- 3). Door's - completed till 20th floors
- 4). Windows - completed till 20th floor
Tower B -
- 1). External sit-out railing - completed all floor
- 2). Tiles work - flooring completed all floor
- 3). Door's - completed till 20th floors
- 4). Window's - completed till 27th floor
Tower C -
- 1). External sit-out railing - completed all floor
- 2). Tiles work - flooring completed all floor
- 3). Door's - completed till 20th floors
- 4). Windows - completed 20th floor
Tower D -
- 1). External sit-out railing - completed all floor
- 2). Tiles work - flooring completed all floor
- 3). Door's - completed till 20th floors
- 4). Window's - completed 11th to 20th floor
Clubhouse - Internal work in progress.
1st November 2023 Report
1st July 2023 Report
A- BLOCK -
- 1). External sit out railing - completed 22nd floor.
- 2). Tiles work - completed 26th floor.
- 3). Fire fighting - completed all floors.
B- BLOCK -
- 1). External sit out railing - completed all floors.
- 2). Tiles work - completed all floors.
- 3). Fire fighting - completed all floors.
C- BLOCK -
- 1). External sit out railing - completed all floors.
- 2). Tiles work - completed all floors.
- 3). Fire fighting - completed all floors.
D- BLOCK -
- 1). External sit out railing - completed all floors.
- 2). Tiles work - completed all floor.
- 3). Fire fighting - completed all floors.
Clubhouse - Internal work in progress.
1st July 2023 Report
1st June 2023 Report
A- BLOCK -
- 1). External sit-out railing - completed 21st floor.
- 2). Tiles work - completed 25th floor.
- 3). Fire fighting - completed 25th floor.
B- BLOCK -
- 1). External sit-out railing - completed all floors.
- 2). Tiles work - completed all floors.
- 3). Fire fighting - completed all floors.
C- BLOCK -
- 1). External sit-out railing - completed all floors.
- 2). Tiles work - completed all floors.
- 3). Fire fighting - completed all floors.
D- BLOCK -
- 1). External sit-out railing - completed all floors.
- 2). Tiles work - completed 26th floor.
- 3). Fire fighting - completed all floors.
Clubhouse - Internal work in progress.
1st June 2023 Report
1st May 2023 Report
A- BLOCK -
- 1). External sit out railing - completed 21st floor.
- 2). Tiles work - completed 23rd floor.
- 3). Fire fighting - completed 23rd floor.
B- BLOCK -
- 1). External sit out railing - completed 27th floor.
- 2). Tiles work - completed 23rd floor.
- 3). Fire fighting - completed all floors.
C- BLOCK -
- 1). External sit out railing - completed 24th floor.
- 2). Tiles work - completed 26th floor.
- 3). Fire fighting - completed all floors.
D- BLOCK -
- 1). External sit out railing - completed 16th floor.
- 2). Tiles work - completed 25th floor.
- 3). Fire fighting - completed 26th floor.
Clubhouse - Internal work in progress.
1st May 2023 Report
1st April 2023 Report
A- BLOCK -
- 1). External sit out railing - completed 17th floor.
- 2). Tiles work - completed 19th floor.
- 3). Fire fighting - completed 23rd floor.
B- BLOCK -
- 1). External sit out railing - completed 27th floor.
- 2). Tiles work - completed 20th floor.
- 3). Fire fighting - completed all floors.
C- BLOCK -
- 1). External sit out railing - completed 20th floor.
- 2). Tiles work - completed 24th floor.
- 3). Fire fighting - completed all floors.
D- BLOCK -
- 1). External sit out railing - completed 14th floor.
- 2). Tiles work - completed 23rd floor.
- 3). Fire fighting - completed 26th floor.
Clubhouse - Internal work in progress.
1st April 2023 Report
1st March 2023 Report
A- BLOCK -
- 1). External sit out railing - completed 17th floor.
- 2). Tiles work - completed 18th floor.
- 3). Fire fighting - completed 21st floor.
B- BLOCK -
- 1). External sit out railing - completed 27th floor.
- 2). Tiles work - completed 19th floor.
- 3). Fire fighting - completed all floors.
C- BLOCK -
- 1). External sit out railing - completed 20th floor.
- 2). Tiles work - completed 22nd floor.
- 3). Fire fighting - completed all floors.
D- BLOCK -
- 1). External sit out railing - completed 14th floor.
- 2). Tiles work - completed 20th floor.
- 3). Fire fighting - completed 26th floor.
Clubhouse - Internal work in progress.
1st March 2023 Report
1st February 2023 Report
A- BLOCK -
- 1). External sit out railing - completed 16th floor.
- 2). Tiles work - completed 14th floor.
- 3). Fire fighting - completed 21st floor.
B- BLOCK -
- 1). External sit out railing - completed 22nd floor.
- 2). Tiles work - completed 16th floor.
- 3). Fire fighting - completed all floors.
C- BLOCK -
- 1). External sit out railing - completed 18th floor.
- 2). Tiles work - completed 18th floor.
- 3). Fire fighting - completed all floors.
D- BLOCK -
- 1). External sit out railing - completed 14th floor.
- 2). Tiles work - completed 16th floor.
- 3). Fire fighting - completed 26th floor.
Clubhouse - Internal work in progress.
1st February 2023 Report
1st January 2023 Report
A- BLOCK -
- 1). External sit out railing - completed 16th floor.
- 2). Tiles work - completed 10th floor.
- 3). Fire fighting - completed 20th floor.
B- BLOCK -
- 1). External sit out railing - completed 21st floor.
- 2). Tiles work - completed 14th floor.
- 3). Fire fighting - completed 26th floor.
C- BLOCK -
- 1). External sit out railing - completed 18th floor.
- 2). Tiles work - completed 16th floor.
- 3). Fire fighting - completed 23rd floor.
D- BLOCK -
- 1). External sit out railing - completed 14th floor.
- 2). Tiles work - completed 12th floor.
- 3). Fire fighting - completed 26th floor.
Clubhouse - Internal work in progress.
1st January 2023 Report
1st September 2022 Report
A- BLOCK - 20th Floor Pour- 1 completed, Pour-2 slab Reinforcement in progress.
B- BLOCK - 27th Floor wall shuttering in progress.
C- BLOCK - G+27th Floors completed.
D- BLOCK - 22nd Floor Pour- 1 completed, Pour- 2 shuttering in progress.
Clubhouse - 5th Floor slab Reinforcement in progress.
1st September 2022 Report
1st September 2021 Report
A- Block : Ground floor to First floor shuttering in progress.
B- Block : Second floor to Third floor wall shuttering in progress.
C- Block : Second Floor to Third Floor wall shuttering in progress.
D- Block : First floor to Second floor wall shuttering in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Clubhouse : 1st Basement to Ground floor level column and Tanks Shuttering and Concrete work in progress.
1st September 2021 Report
1st September 2020 Report
A- Block Raft Reinforcement in Progress
B- Block Raft Reinforcement in Progress
C- Block Basement 3 & 2 Level Column concrete in Progress
D- Block Raft PCC completed
* Work in progress with adequate work force even in pandemic situation.
1st September 2020 Report
18th February 2020 Report
Excavation For 3 Basements Completed.
18th February 2020 Report